β Checklist before commissioning
A commissioning goes well when all the information is gathered before going on site. This checklist lists what to ask the customer, their electrician and their IT department, in the order the Console will need it. It follows the path described in Commissioning a site, step by step.
π’ 1. The customer and the siteβ
This information is used to create the customer company (Companies > Create customer company) then the site (Sites > Create site).
| Information | Console field | Note |
|---|---|---|
| Customer company name | Company name | Example: Nordhem |
| Company email and phone | Email, Phone number | Phone in international format: +3242457692 |
| VAT number, company number | VAT number, Company number | Optional |
| Company address | Street name, Number, Box Number, Postal code, City, Country | Country is Belgium by default |
| Site name | Site name | Must start with the company name: Nordhem Hognoul. See The site |
| On-site contact | Contact email, Contact phone number | The person to notify for the site |
| Site address and GPS coordinates | Address block, then Latitude and Longitude | The Click to Fill in latitude and longitude coordinates based on address link calculates the coordinates from the address; if it fails (recent or poorly known address), read them off a map and enter them |
| EAN code of the connection point (Belgium) | EAN | 18 digits, for example 541448912345678912; useful for Energy Units reports |
| Public access to the charge points (Belgium) | Charge point access | Public, Semi Public or Private (default); useful for Energy Units reports |
π₯οΈ 2. The controller, the hosting mode and the licencesβ
| Information | Why | Where to get it |
|---|---|---|
| Hosting mode: Edge, Hybrid or Cloud | Determines the hardware to install and the network to plan | See Choose the hosting mode |
| Controller (Edge) or gateway (Hybrid) available | A site is attached to a free controller of the same mode | Delivered by Fuzz after agreement; contact support@fuzz.energy |
| Serial number of the controller | To choose in Fuzz Controller's serial number | MAC address of the eth0 port, on the label of the enclosure |
| Required licences: Timeseries Database (history), Monitoring & Alerting (alerts, reports), Energy Units Reports (Belgium) | Without a licence, these menus do not appear | Ask Fuzz to enable them before commissioning. See Licences |
β‘ 3. The grid connection and tariffsβ
| Information | Console field | Note |
|---|---|---|
| Maximum connection power (kW) | Maximum Power (kW) of the grid | The limit that smart charging will never let be exceeded. Without a main meter, enter the share reserved for charging. See Smart charging |
| Distribution system operator (DSO) | Distribution System Operator | Fluvius, RESA, ORES, Sibelga or Other |
| Peak / off-peak time ranges | Off-peak schedule | Single Rate, Dual Rate (10 PM-7 AM + weekends) by default, Dual Rate (9 PM-6 AM + weekends), Dual Rate (11 AM-5 PM + 10 PM-7 AM), Triple Rate / IMPACT |
| Connection level | Electrical connection level | Low voltage up to 56 kVA, above 56 kVA, Trans-LV, medium voltage, Trans-MV, high voltage |
| Capacity tariff | Capacity tariff | Yes or no. Ticked, Fuzz measures and limits the site's quarter-hour peak. Also note, from the bills, the monthly peak and the annual peak of the last months: they are used to start the limit without waiting for a month of measurement. See Grid tariffs: capacity tariff |
| Buying and selling price formulas | Buying price formula, Selling price formula (peak, off-peak, medium) | According to the energy contract: X * Belpex + Y, X * Belix + Y or fixed price |
| VAT rate and deductible VAT | VAT rate (%), Deductible VAT rate (%) | 21% and 100% by default |
π See: Grid tariffs
π³ 4. The electrical topologyβ
Smart charging only protects properly what it knows. Ask for the up-to-date single-line diagram and note:
- the main low voltage switchboard and its rating per phase (A);
- each sub-switchboard that supplies charge points or controlled assets, with its rating (A) and the switchboard that supplies it;
- the existing meters or those to be installed, and the switchboard they measure; at a minimum, plan a meter on the main switchboard if you want solar surplus or to take the building's other consumption into account;
- for each charge point, the switchboard that supplies it, the number of phases and the phase connection order (rotation).
π See: Electrical topology survey
π 5. The list of assetsβ
For each asset, note:
| Asset | What to note |
|---|---|
| Charge point | Make, model, serial number, number of connectors, power and maximum current per connector (A), number of phases, accepted minimum current (often 6 or 7 A), support for OCPP 1.6J and OCPP smart charging, access to its configuration page (IP address, installer login provided by the manufacturer), EMI3 identifier if Energy Units reports are used |
| Meter | Make, model, protocol (Modbus TCP, Modbus RTU or MQTT), maximum current (A), switchboard measured |
| Photovoltaic inverter | Make, model, protocol, maximum current (A), peak power, controllable or not |
| Battery | Make, model, protocol, capacity (kWh), maximum charge and discharge currents (A), desired state of charge limits (%) |
| Fridge, other Modbus asset | Make, model, protocol, Modbus register documentation |
Communication data by protocol:
- Modbus TCP: fixed IP address, port (502 by default), Modbus identifier (Unit ID).
- Modbus RTU (RS485): Modbus identifier, speed (baud rate, 9600 to 115200, often 19200), parity, data bits, stop bits; all the assets on the same bus must have the same settings.
- MQTT: the broker used and the topics published.
- Asset web interface: IP address, HTTP or HTTPS protocol, port.
Check each model in Compatible hardware. A model that is not in the list requires Fuzz's opinion before ordering.
π 6. The IT networkβ
Send the page IT network to the customer's IT department and obtain:
- a network socket for the controller, with outbound Internet access;
- its IP address: fixed (DHCP reservation on the MAC address, or address entered in the installer menu) as soon as there are OCPP charge points on the local network;
- the firewall openings towards the Fuzz servers;
- fixed IP addresses for the Modbus TCP assets and for the assets whose web interface you want to open remotely;
- for charge points connected through the Internet (Hybrid, Cloud, or exposed Edge site): their Internet access (site network or SIM card).
πͺͺ 7. Charging authorization, badges and CPOβ
| Information | Note |
|---|---|
| Authorization mode of each charge point | Plug & Charge (no badge), Local (whitelist badges), CPO, Local then CPO. See Charging authorization |
| List of badges | Identifier (ID Tag), first name, last name, priority, active. A CSV file can be imported in one go (columns idTag, firstName, lastName, priority, active, priceModulationEnabled, priceHigh, priceLow, priceModulationDelaySec). See Badges (ID tags) |
| CPO, if any | CPO name, protocol (OCPP or REST), URL provided by the CPO, identifier of each charge point at the CPO (CPO Station ID), default badge to declare at the CPO |
| Desired priority rules | Priority badges or charge points, charging on solar surplus, modulation by price. See Smart charging |
π₯ 8. Users and alertsβ
- Customer users: name, first name, email and role of each person (Reporting for the site manager, IAM Administrator for the person who creates their colleagues' accounts, Read Only for viewing). See Users, groups and roles.
- Alert recipients: email addresses, Telegram group or webhook URL, and the situations to report (charge point in fault, asset offlineβ¦). See Notification channels.
- Your team's access: which groups in your company must have access to the customer (the Manage access step of company creation).
ποΈ Checklist summaryβ
- Customer company details and site name (starts with the company name)
- Hosting mode chosen, controller or gateway available, serial number noted
- Licences requested from Fuzz
- Connection power (kW), DSO, tariff time ranges, price formulas
- Single-line diagram, switchboard ratings, meters, charge point phases
- List of assets with make, model, protocol and communication data
- Network prerequisites sent and validated by the customer's IT
- Authorization mode, list of badges, CPO data
- Customer users and their roles, alert recipients