🌳 Electrical topology survey

To configure a site in Fuzz, you must reproduce its electrical diagram in the Console (the topology) and know the communication data of each asset. This page explains what to survey on site or on the plans, and in what form, before commissioning. To understand why this information matters, see Assets and electrical topology.


πŸ—ΊοΈ 1. Start from the single line diagram​

Ask for the up-to-date single line diagram of the installation. It must show:

  • the grid connection point and its maximum power (kW), or the rating of the head circuit breaker;
  • the main low voltage switchboard and its rating per phase (A);
  • each sub-switchboard that supplies charge points or assets that Fuzz must control or measure, with its rating and the switchboard that supplies it;
  • the busbars and circuit breakers that limit a group of charge points;
  • the power and rating of each charge point, of the photovoltaic installation and of the battery;
  • the existing meters and what they measure.

Then translate it into a tree, from the grid to the assets. Example for Nordhem Hognoul:

Grid : 100 kW connection
└── Main low voltage switchboard : 160 A, meter "Compteur principal" (main meter)
β”œβ”€β”€ Tableau parking (parking switchboard) : 125 A
β”‚ β”œβ”€β”€ Borne P1 (charge point P1, 2 connectors of 32 A, three-phase)
β”‚ └── Borne P2 (charge point P2, 2 connectors of 32 A, three-phase)
β”œβ”€β”€ Toiture photovoltaΓ―que (rooftop PV) : 80 A
└── Batterie de stockage (storage battery) : 50 A, 100 kWh

A switchboard that supplies nothing Fuzz knows about does not need to be described. However, a switchboard that limits a group of charge points (for example a 125 A parking switchboard) must be, even if it has no meter.


⚑ 2. Switchboards and meters​

For each switchboard to describe, note:

InformationExampleConsole field
NameTableau parkingSwitchboard name
Switchboard that supplies itMain low voltage switchboardPosition in the topology
Rating per phase125 AMaximum current (A)
Meter that measures it, if anyβ€”Meter

Fuzz applies a margin (Correction factor, 95% by default): it controls a 125 A switchboard at 118.75 A at most. Enter the real rating; the margin is set afterwards in the Console.

Main meter. A meter on the main switchboard lets Fuzz see the whole building's consumption and the photovoltaic injection. It is not mandatory, but without it charging on solar surplus is not possible and the limits must be reduced to the share reserved for charging. See Smart charging without a main meter.


πŸ”Œ 3. The information for each asset​

For each asset (charge point, meter, inverter, battery, fridge, other Modbus asset), note:

InformationExample
Name in FuzzBorne P1 - Connecteur 1
TypeCharge point, Meter, Photovoltaic, Battery, Fridge, Generic modbus
Brand and modelAlfen S-Line, Phoenix Contact EEM-MA371, Huawei SmartLogger
Switchboard that supplies itTableau parking
Maximum current per phase32 / 32 / 32 A
Number of phases3 (or 1 for a single-phase charge point)
Phase wiring order (phase mapping)L1/L2/L3, or L2/L3/L1 if the phases have been rotated
Communication protocolOCPP, Modbus TCP, Modbus RTU, MQTT

Check that each model appears in Compatible hardware: the model chosen in the Console (Model) decides which measurements Fuzz can read.


πŸ” 4. Survey the phase order (phase mapping)​

Fuzz calculates each phase separately. It must know which grid phase each phase of an asset is wired to.

  • Direct wiring: L1 of the asset on L1 of the grid, L2 on L2, L3 on L3. Note L1/L2/L3.
  • Rotation: to balance a switchboard, the electrician often shifts the phases from one charge point to the next. Note the real order. For example L3/L1/L2 means:
    • L1 of the asset β†’ L3 of the grid;
    • L2 of the asset β†’ L1 of the grid;
    • L3 of the asset β†’ L2 of the grid.
  • Single-phase charge point: note the grid phase it is wired to (for example L2).

A wrong phase mapping can let a phase of a switchboard overload while Fuzz believes the load is balanced. Take the time to survey it at the switchboard.

πŸ‘‰ See: Settings common to all assets


πŸ”— 5. Communication data​

Depending on each asset's protocol, note the data that lets the controller reach it.

Modbus TCP assets​

InformationDefault value in the Console
IP address of the asset (fixed)192.168.0.1
Modbus port502
Unit ID (the asset's Modbus identifier)To be found in the asset's configuration

Several assets behind the same Modbus gateway (for example a SmartLogger) share the IP address and are told apart by their Unit ID.

Modbus RTU (RS485) assets​

InformationRemark
Serial port usedThe RS485 port of the controller (or of the Hybrid gateway), or a USB adapter
Unit IDUnique on the bus
Baud rate (speed)9600, 19200 (default), 38400 or 115200
Parity, Data bits, Stop bitsIdentical for all assets on the same bus

Also note the bus wiring (order of the assets, end-of-line resistor). See Modbus assets (TCP and RTU).

OCPP charge points​

InformationRemark
Serial number of each charge point (station)To name it and find it again; some charge points require it in their OCPP URL
Number of connectorsOne Fuzz charge point per connector
Support for OCPP 1.6J and OCPP smart chargingEssential for Fuzz to limit the current
Access to the charge point configurationManufacturer's app or web interface, installer credentials provided by the manufacturer
Authorization modePlug & Charge, Local, CPO or Local then CPO. See Charging authorization
CPO, if anyCPO URL and the charge point's identifier at the CPO (CPO Station ID)
EMI3 identifier (Belgium, Energy Units reports)EMI3 Identifier

πŸ‘‰ See: OCPP configuration of charge points

Assets with a web interface​

Many assets have a configuration page reachable over the local network, which the Console can open remotely (Open Secure Tunnel button). Note:

  • the local IP address (fixed);
  • the protocol: HTTP or HTTPS;
  • the port, if it differs from 80 (HTTP) or 443 (HTTPS).

πŸ‘‰ See: Open the web interface of an asset remotely


πŸ“ 6. Example survey sheet​

Sheet for the Nordhem Hognoul site, as it can be prepared before commissioning:

NameTypeSupplied byMax currentPhasesProtocol and addressRemark
GridGridβ€”100 kWβ€”β€”Connection power
Main low voltage switchboardSwitchboardGrid160 Aβ€”β€”Meter: Compteur principal
Compteur principalMeterMain low voltage switchboard160 AL1/L2/L3Modbus TCP, fixed IP, port 502, Unit ID 1
Tableau parkingSwitchboardMain low voltage switchboard125 Aβ€”β€”No meter
Borne P1 - Connecteur 1 and 2Charge pointTableau parking32 A3, L1/L2/L3OCPP, station Borne P1Authorizer Plug & Charge
Borne P2 - Connecteur 1 and 2Charge pointTableau parking32 A3, L1/L2/L3OCPP, station Borne P2Authorizer Plug & Charge
Toiture photovoltaΓ―quePhotovoltaicMain low voltage switchboard80 AL1/L2/L3Modbus TCP, fixed IP, port 502, Unit ID 1
Batterie de stockageBatteryMain low voltage switchboard50 A charge / 50 A dischargeL1/L2/L3Modbus TCP, fixed IP, port 502, Unit ID 1100 kWh

πŸ‘‰ Next step: Commissioning a site, step by step