π Meters
An electricity meter gives Fuzz the real measurements of a part of the installation: current per phase, voltage, power, energy. The most important one is the main meter, which measures what the site draws from the grid or feeds into it. This page explains where to place meters in the topology and how to connect them. The full form is described in Add a meter.
β Prerequisitesβ
| Item | Required |
|---|---|
| Meter | A model from the list of compatible meters, connected using Modbus TCP, Modbus RTU or MQTT |
| Hosting mode | Modbus: Edge or Hybrid. MQTT: all modes (see MQTT devices) |
| Role | Administrator or Operator of the site |
| Topology | The switchboard the meter is attached to already exists (see The Topology page) |
π― The main meter and its roleβ
The main meter is the meter attached to the Main low voltage switchboard, just behind the grid connection point. It measures the exchange with the grid: what the site imports, or exports when solar production exceeds consumption.
Thanks to it, Fuzz:
- respects the maximum power of the connection (Maximum Power (kW) of the grid) by taking into account the whole consumption of the building, not only the charge points;
- knows when the site is exporting solar surplus, and can then charge the vehicles whose priority is 10 or 15 to 19 (solar surplus charging, see Charge vehicles on the solar surplus);
- displays the GRID FLOW: IMPORT/EXPORT [kW] and MAIN METER flow in the Energy flow diagram of the site Overview page.
Without a main meter, smart charging still works, but Fuzz cannot see the consumption of the rest of the building or the export: priorities 10 and 15 to 19 are treated as priority 20 (no charging reserved for solar surplus). See Smart charging: how Fuzz distributes power.
In the Nordhem Hognoul demo site, the meter Compteur principal is attached to the Main low voltage switchboard (160 A).
ποΈ Where to place the other metersβ
A meter can be attached to:
| To | How | Use |
|---|---|---|
| A secondary switchboard | Meter field of the switchboard form (or Add a new meter link) | Measure the real consumption of a feeder, for example the car park switchboard, to respect its Maximum current (A) |
| An asset (photovoltaic, battery, fridge, generic asset) | Meter field of the asset form | Measure this asset when it does not provide its own measurements. Do not choose a meter for an asset that already measures itself ("Select a meter only if the asset isn't itself one") |
A meter is created from the Topology page (Create asset button, then Meter) or directly from the Meter field of a switchboard or an asset, with Add a new meter > Meter (physical device).
When no meter can be installed where it is needed (at the head of the installation, for example), a virtual meter computes the measurement from other assets, each one added or subtracted: for example the exchange with the grid TGBT β Photovoltaic, or the building consumption without the charge points. It is created from Create asset > Virtual meter or Add a new meter > Virtual meter (computed from assets). See Virtual meter.
π₯οΈ Declare the meter in the Consoleβ
The form of a meter has three steps: Meter, Phase mapping and Console.
| Field (Meter step) | Meaning | Default |
|---|---|---|
| Meter name | Name of the meter, unique on the site | β |
| Protocol | Modbus or Mqtt | Modbus |
| Model | The model of the meter in the Fuzz list | β |
| Maximum current (A) | Maximum current per phase at the measured location, for example 160 for a 160 A main low voltage switchboard | empty |
| Modbus configuration | IP address, port, unit ID (TCP) or serial port and bus settings (RTU): see Modbus assets | β |
| MQTT broker, MQTT variables | For an MQTT meter: see MQTT devices | β |
At the Phase mapping step, Assign phase for L1/L2/L3 states which site phase each meter input corresponds to, and Reverse current for L1/L2/L3 reverses the direction of a measurement when a current transformer is fitted the wrong way round. The Console step lets you open the meter web interface remotely.
π Check a meterβ
- Assets, State tab, Meters filter: the meter is Online, with values in P (W) and I1 (A), I2 (A), I3 (A).
- On the main meter, compare the direction of the power with the real situation: a site that is consuming must show an import in Energy flow. If the direction is reversed on a phase, correct it with Reverse current for that phase.
- Compare the currents with those of a clamp meter: a large difference indicates a wrong current transformer ratio on the meter or a wrong phase assignment.
| Symptom | Probable cause | Solution |
|---|---|---|
| The meter is offline | Address, unit ID or RS485 bus | See Common Modbus problems |
| Export displayed while the site is consuming | Current transformer fitted the wrong way round | Reverse current on the phase concerned |
| Currents at zero on a phase | Phase not connected or wrongly assigned | Check the wiring and Assign phase |